The relevant
legislation and guidelines in both Mainland China and HKSAR will be followed in
setting design criteria for the Project.
In accordance with the PRC National Standard Flood Prevent Standard (GB 50501-94) and Urban Flood Prevent Engineering Design Standard (CJJ50-92), the
design return period for
2.2
Flood Prevention Measures Analysis
With an
attempt to increase the hydraulic capacity of the concerned section of the
·
Flood storage: construct of
flood storage tank / pond upstream or retardation pond along the relevant
sections of the river;
·
Flood diversion:
construct of a floodway to divert significant amount of rainwater away
from the overflowed river; and
·
River modification works:
such as river widening, raising of river embankment and river deepening
to increase the sectional area and hence the drainage capacity of the river.
A comparison of these flood prevention measures are
summarized in Table 2.1.
Table 2.1 Flood
Prevent Measures Comparison
Flood Prevent Measures |
Effect on Flood Prevention |
Limitation |
Recommendation |
River modification works |
Significant |
Require additional land along the
river |
A combination of river widening,
deepening and raising of river embankment is recommended |
Flood Storage Pond along the river |
Low – cannot attain the drainage
capacity of a 50-year return period if use alone |
Require additional land along the
river |
Could be used in conjunction with river
modification works |
Flood Storage Tank at upstream |
Low/medium – cannot attain the drainage capacity of
a 50-year return period if use alone |
Involve construction works outside the relevant
section of |
Not recommended for this Project |
Flood Diversion to outer tributaries |
Significant |
Involve construction works outside the relevant
section of |
Not recommended for this Project |
Based on the preliminary assessment of different
flood prevention measures, a combination of river modification works and flood
retardation pond was taken forward to study the preferred option for the Stage
4 regulation works.
An options
evaluation exercise has been conducted with the purpose of identifying a
technically feasible, cost-effective and environmentally & socially acceptable
option of the Stage 4 regulation works.
A hydraulics model, MIKE 11 developed by the Danish Hydraulics Institute
(DHI), was used to assess the effects of different design options on the
hydrology and hydraulics of
2.3.1
Flood
Prevention Options
The design
principle of the works is to protect the livelihood of residents on both sides
of the river with an ecological sensible design, which should maintain the
naturalness of the river and riparian habitats and hence protect the
biodiversity. The design and layout
planning of the works should be compatible with the future LT/HYW BCP. Two design options were then developed for
further study:
Option
A: The existing
alignment of the concerned section of the
Option
B: The concerned
sections of the
The
alignment and land requirement of both options are shown in Figure
2.1.
2.3.2
Evaluation
Aspects
Land Requirement
The
construction of flood retardation ponds and river widening works would require
extra land along the relevant sections of the
The design
of the regulation works should avoid the need of demolition of existing patrol
roads and minimize the potential impacts on the adjacent villages such as Heung
Yuen Wai and Chuk Yuen and
the associated Fung Shui Woodland and graves.
The land
requirements under the two options are summarized in Table 2.2. Option A would
require less additional land then Option B and can achieve a more balance
approach in term of land use in both
Table 2.2 Land
Requirement Summary
Option |
Land Requirement (m2) |
||
|
Shenzhen Side |
Hong Kong Side |
Total |
Option A |
129,190 (44%) |
163,250 (56%) |
292,440 |
Option B |
129,160 (41%) |
182,500 (59%) |
311,660 |
Environmental Consideration - Ecological Friendly Design
Option A
will minimize the alternation of the existing river alignment and the
meandering nature of the river will be preserved. In addition, the existing channel, river side
land and embankments will be maintained as far as practical which will provides
different natural aquatic and riparian habitats to support local ecology. This option will also avoid massive
excavation and filling works and hence will minimize potential dust and noise
impacts during the construction phase.
On the
other hand, Option B will involve widening, straightening and sectional
modification of the concerned river sections.
The alternations will reduce the current winding nature of the river. The river will be mainly in the form of
trapezoid channel and the river bank habitats are expected to be man-made in
nature after the modification works.
The slope
works on the river embankment will be integrated with landscape design to re-establish the natural riparian
ecosystem with the aims to enhance the local biodiversity, protect the water
resources and avoid erosion.
Environmental Consideration - Fill Balance
The
expected quantities of excavated materials and filling requirement of two
options are summarized in Table 2.3. Based on the preliminary study, it is
estimated that about 610,000 m3 and 651,300 m3 of
materials will be excavated and about 102,000 m3 and 143,500 m2
of those materials can be reused on-site as backfilling materials for Option A
and Option B respectively. The
preliminary sediment quality investigation results show that Option A and
Option B would require disposal of 508,000 m3 and 507,800 m3
of surplus materials, respectively.
Table 2.3 Fill
Balance in Two Options
|
Item |
Option A (m3) |
Option B (m3) |
1 |
Excavated materials |
610,000 |
651,300 |
2 |
Backfilling materials required |
102,000 |
143,500 |
3 |
Surplus materials for off-site disposal |
|
|
|
- Uncontaminated soil |
410,000 |
416,700 |
|
- Contaminated sediments |
98,000 |
91,100 |
Note: (a)
These
quantities were estimated during the option evaluation stage. The updated fill balance quantity for the
preferred option after preliminary design consideration shall refer to
Section 9 of this EIA Report. |
Environmental Consideration - Air and Noise Impacts during Construction
The works area and the quantity of the excavated materials in Option A will be smaller than Option
B. It is also expected that the number of
construction plants needed under Option A, and hence the potential construction
dust and noise impacts during construction, will be less than Option B.
Environmental Consideration - Landscape and Visual Considerations
Compare with Option B, Option A will minimize the alternation of the existing river alignment
and the meandering nature of the river will be preserved.
Both options will consist of a flood retardation
pond. The pond will be designed with
distinctive landscape features including three small isolated islands to create
a winding flow of water. Proper
landscape will be provided on these islands.
Management and Maintenance during Operation
It is
expected that the regular clearing of refuse and desilting
will be required to maintain the normal operation of the river. The design of the inlet and outlet of the
flood retardation ponds are based on overflow weir or gates with automatic
control system and it is anticipated that limited management resources would be
needed. Patrol roads connecting the main
access road and the rest of
Cost
Based on
the preliminary design of the two options, the estimated costs (excluding the
cost for land resumption) are summarized in Table
2.4.
Table 2.4 Costs
of Two Options
|
Major Work Items |
Option A (RMB ¥) |
Option B (RMB ¥) |
1 |
River Regulation |
486.5 million |
512.5 million |
2 |
Patrol road and boundary fence
- Shenzhen side (includes
CCTV) |
19.8 million |
19.8 million |
3 |
Patrol road and boundary fence
– |
77.6 million |
76.5 million |
|
Total |
586.9 million |
608.8 million |
2.3.3
Construction
Sequence and Methodology
The reprovisioning of
boundary patrol road on
The river modification works will be carried out in
four phases, commencing from the downstream section of the river. Two phases will be carried out in
parallel. This approach will strike a
balance between the need to control the magnitude of environmental impact at
the same time while not hindering the overall programme of the Project. Heavy rains during wet and typhoon seasons
will increase the quantity of site runoff during construction. In order to minimize the potential water
quality impacts, river dredging works will be arranged to be conducted in dry
seasons.
River sediment will need to be dredged during the
river modification work. Due to the site
constraints and the shallow water depth, the use of dredging barge in this Project
is not feasible. Land based dredger will
be used.
With regard to river bed excavation, instead of
directly excavating the river bed, which will generate sediment plume release
to the river water throughout the excavation period, the excavation of river
bed for this Project will be carried out within a cofferdam made of hessian
bags. By implementing this method, the
cofferdam will block the sediment released into the river during the excavation
work (ie work in dry condition), thus minimising the
water quality impact. River diversion
work will be carried out before the commencement of excavation and construction
works. When the excavation and placement
of embankment foundation are carried out on one side, the river course on the
other side will be used as diversion channel.
This method will ensure the seamless flow of water along the river and
minimise the disruption of hydrology of the river.
The construction sequence and methodology for both
options will be the same.
2.3.4
Summary
of Options Evaluation
A summary
of the option comparison is presented in Table
2.5. The environmental benefit and disbenefits of both options are also summarised in Table 2.6.
Table 2.5 Summary
of Options Evaluation
Issue / Criteria |
Option A |
Option B |
Preferred Option |
Land Requirement |
29 ha of which 44% in Shenzhen side and
56% in |
31 ha of which 41% in Shenzhen side and
59% in |
Option A |
Environmental
Consideration - Ecological
Friendly Design |
Minimize
the alteration of the existing river alignment; provides diversified river
and riparian habitats to support the local ecology along the modification
section |
Widening,
straightening and sectional modification of the relevant river section; will
provide similar river and riparian habitats along the modification section |
Option
A |
Environmental
Consideration - Fill Balance |
About
0.508 Mm3 surplus materials required off-site disposal |
About
0.508 Mm3 surplus materials required off-site disposal |
No
significant difference (but less earthwork for Option A) |
Environmental
Consideration - Air and Noise Impacts during Construction |
Less
construction plants needed and hence less air and noise impacts during
construction |
More
construction plants needed and hence more air and noise impacts during
construction |
Option
A |
Environmental
Consideration - Landscape and Visual Impacts |
Minimize
the alternation of the river and hence preserve the existing landscape
character area. |
Extensive
modification works will cause permanent loss of existing landscape character
area |
Option
A |
Management and Maintenance during
operation |
Management and maintenance would be
simple and in low costs |
Management and maintenance would be
simple and of low costs |
Same |
Cost |
586.9 million |
608.8 million |
Option A |
Table
2.6 Summary of Environmental
Benefits and Dis-Benefits of the Design Options
Options |
Environmental Benefits |
Environmental Dis-Benefits |
A |
·
Follow
the existing alignment as much as possible and hence preserve the existing
landscape character better ·
Less
earthworks (excavation and fill) required and thus use less construction
plant and hence less dust and noise impacts ·
Smaller
land requirement area which means less direct impact on existing habitats |
·
Will
disturb the existing habitat but the impact will be localised ·
Nuisance
during construction period but will be mitigatable |
B |
- |
·
Will
disturb the existing habitat but the impact will be localised ·
Nuisance
during construction period but will be mitigatable ·
More
earthworks required ·
Use
more construction plant and hence more dust and noise impact ·
More
habitat loss |
Both Option
A and Option B are designed to attain the drainage capacity of a 50-year return
period. The management and maintenance
of both options will be simple and of low costs and the design and layout
planning of both options will be compatible with the proposed LT/HYW BCP.
Although
the alignment under both options have no significant difference, the alignment
of Option A follows closer to the existing river alignment and hence performs
better in terms of maintaining the river profile and landscape character. Option A also requires less additional land
than Option B especially the use of land in
As a
result, Option A is preferred in terms of land requirement, environmental
consideration and cost implication and will be adopted as the design scheme for
detailed design and EIA Study.